Cautions
for calory meter and heat meter installation
|
|
Calory
meter, heat meter in a interior place and secure enough space for easy
repairing & checking.
Install
in a place that is away from high humidity, dust, impact & direct
sunlight.
Install
the indicator in a place that is easy to check.
Pipe
has to be install between a calculator part and a display part and keep
min. length.
It has to be straight as much as possible and keep away from substances
by protector.
Install
calory meter --on return side and strainer (about 40 mesh) on forward
meter to protect flow part.
Install
the valve on each inlet and outlet side of meter (include strainer)
|
|
Cautions
before installation
|
|
Install
all accessaries (Union, Nut, Sensor pocket, strainer) exclusive of main
part (calory meter, water meter) firstly.
Install
a temporary pipe instead of flow part.
Open
all valves and remove the substance inside. (Flushing 6 times)
Change
water several times and check the substances inside.
At
this time, clean strainer.
|
|
Caution
on installation
|
|
After
complete above process, remove a temporary pipe and install the meter.
At this time, check the direction of water flow.
Insert
the sensor for supply and the sensor for return into pocket correctly,
tie the fixed piece softly.
In
the case of the remoting display type, please remove the order cause
by wire cut after inserting cable install caulking at the calculating
part and bushing at display part.
When
you connect calculator part with indicator part by cable, please connect
in accordance with same color of cable.
Please
connect the cable tightly to peel the cable.
|
|
Caution
of transport and handling
|
|
Calory
meter, heating water meter are precision instruments and so avoid the
excessive vibration or outside impact.
Transport
the indicator in a box certainly.
Please
be careful the demage of cover and don't press the excessive force during
install of piping.
|
|
Other
caution
|
|
For
smooth working of calory and water meter, after flushing as the method
like the upper " working before installation" before working
heating per year, please do heating.
Please
change the heating water 2 times per year.
After
testrunning, please seal on detecting part (Sensor for supply, sensor
for return).
|
|
|
|
|